A Not To Exceed (NTE) EPO is a purchase order where the exact amount
is not known but the supplier has guaranteed that it will not exceed a
specified amount. When creating an NTE EPO, the user will enter the amount
of the EPO that should not be exceeded. If the NTE amount exceeds the
user’s EPO approval limit, then the normal approval process will
be followed. Once the work has been completed, the construction manager
will enter the actual amount from the invoice. This amount cannot be more
than the original ”Not to Exceed” amount. A Back Charge may
be added to an NTE EPO.
Choose a task from the Copy
Task drop-down list. A task name automatically appears in the New Task Name field that includes the
text NTE EPO.
Edit the New Task Name
if necessary.
In the Request Date
field, enter the date the EPO items are needed.
Choose the appropriate supplier for this task from the
Supplier from the drop-down list
Click the EPO Reason
field and choose the appropriate reason for this EPO.
Click the Schedule
Change Reason field and make the appropriate selection.
Type any relevant notes in the Supplier
Instructions field.
Complete the EPO Task
Notes (to backoffice) field with any relevant information.
In the EPO Items
section, you must add at least one item. Complete the fields in the SKU, Description,
and NTE Amount columns
with the line items needed on the purchase order.
If the task has options, you can choose an Option
for each line item from the drop-down list next to the Description
column.
If the EPO is ready to be submitted for approval, click
the EPO Ready check box in the
bottom left of the page
Click the Create EPO
button. The new EPO task is added
and the Job
Task page appears.